Interested Contractors,

Below is a Dropbox link to the construction documents/bid documents for the Project Elkhorn Public Schools, Elkhorn High School (EHS) – Softball-Baseball Complex Restrooms & Storage Building.

https://www.dropbox.com/scl/fo/erpw60oalaqr9g656g13l/h?dl=0&rlkey=8i5rvxf9ut5g9vmlpyt9q407x

Project Schedule:

Monday May 1, 2023…………………… Construction Documents Available

Wednesday May 3, 2023…………………… Mandatory Pre-Bid Walk Through on-site at 10:00 A.M.

Monday May 8, 2023………………….Receive Bids at Elkhorn Public Schools, 10:00 A.M. in the Elkhorn Public Schools, Teacher Training Conference Center, Room 3, located at 20650 Glenn Street, Omaha, Nebraska 68022

Summer 2023…………………… Construction Begins On-site

Project Information:

  • New and Existing Building Modification Project
  • New Restroom Storage Building is two stories each level approximately 590 sq.ft.
  • Single wythe masonry exterior walls – Level One
  • Cast in Place Concrete foundation walls
  • Hollow Core Floor structure
  • No Sprinkler System
  • No HVAC heating/Air Conditioning